Construction Projects at PLU

Tingelstad


 

Tingelstad Remodel

The Tingelstad Hall renovation was completed on August 26, 2007.  The residence hall, which was originally built in 1967, received its largest remodel to date.

Tstad

Newly Renovated Tingelstad
Planning and Construction Process


Tingelstad, Remodeled

Tingelstad Hall was started in May 2007 and finished August 26, 2007, and the renovations included:

  • New double pane thermal glass windows throughout the building.
  • A complete building sprinkler system for fire safety
  • New resident room heaters
  • New first floor common spaces
  • New exterior lighting
  • New floor tiles in student rooms
  • New recycled and recyclable carpet in hallways and common rooms
  • Low flow plumbing and dual flush toilets throughout the building
  • New furniture for rooms and lounges
  • New mailboxes
  • New paint

Back to top

Planning and Construction Process

The Tingelstad Hall remodel was overseen by John Kaniss, PLU Construction Management, working with Facilities Management and Finance and Operations.

From October 2006 to January 2007, Mithun, project architect, worked with PLU to design the plans. Pease Construction began construction in May 2007.

The project was completed August 26, 2007.

Back to top





Related Links

Pease Construction

Mithun

Office of Finance and Operations

Residence Hall Improvements

Tingelstad -2007

Pflueger- 2006

Foss- 2005

Ordal- 2004

Stuen- 2003

Coming Soon!

Hinderlie, Hong, and Kreidler

New Tingelstad lobby


New Tingelstad, common area


New Tingelstad bathrooms 2

New Tingelstad bathrooms 1