| Capital Improvements Project | Projected Cost | Current Costs as of 05/31/2016 |
|---|---|---|
| Athletic Fields Restroom | $100,000 | 48.792 |
| Hauge Classroom Upgrades (211A & 211B) | $40,000 | 29,362 |
| Hong/Harstad mailbox swap/replace | $6,000 | 9,402 |
| Humanities Renovation (Hauge 201, 203, 205) | $455,000 | 520,948 |
| Library Instruction Center upgrade | $35,000 | 28,494 |
| Olson Facelift | $52,000 | 60,142 |
| Ramstad Schematic Design | $45,000 | 24,733 |
| Rieke Innovative Learning Space | $32,000 | 25,457 |
| Sidewalk/Crosswalk (122nd & Park-Pierce Co Grant) | $64,800 | 54,056 |
| South Hall Carpet & Paint | $144,450 | 47,098 |
| Emergency Notification System | $95,000 | 90,802 |
| Total | $1,090,000 | $941,127 |